Project Time Management
Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e
7-1
Developing the Project Schedule
• The project schedule is a chart that graphically depicts the sequence, interdependencies and start and finish times of the project.
• The project schedule also depicts the activities to enable the identification of the critical path.
• The project schedule allows for tracking time variances when the project is being executed.
Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e
7-2
From Work Package To Network
Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e
7-3
Activity-on-Node (AON) Fundamentals
• A = Sequences
• B = Burst
• C = Merge
• D = Parallel
Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e
7-4
Sequence the Activities
Copyright © 2013 McGraw-Hill Education (Australia) Pty Ltd Pearson, Larson, Gray, Project Management in Practice, 1e
7-5
...